A screening model, not a bankable feasibility study.

The website uses transparent first-pass energy and employment assumptions so readers can see what would have to be true for the concept to work.

Core screening assumptions

VariableScreening valueWhy it matters
Annual operating hours8,760 hConverts MW into annual energy.
Representative IT load factor85–95%AI loads are high, but not perfectly flat.
Recoverable useful heat65–80 GWh/y per 10 MW IT blockAllows for capture and distribution losses.
Permanent direct roles35–55/site Phase I; 45–75/site Phase IICombines compute and agricultural operations.
Primary powerBC gridSolar is supplemental, not the firm resource.
Water coolingNo once-through river cooling assumedReduces hydrological and thermal-discharge risk.

What can break the model?

Insufficient grid capacity, expensive substation upgrades, lack of carrier diversity, seasonal mismatch between server heat and customers, land-use restrictions, agricultural water constraints, flood or wildfire risk, community opposition, or a failure to secure commercially viable compute customers.

What makes it stronger?

Sites with existing greenhouses or processors, short heat-pipe distances, staged utility connections, multiple fibre carriers, strong local workforce capacity, and counterparties willing to sign long-term heat or food agreements.

Next engineering work

  1. Utility pre-application and feeder/substation screening for every node.
  2. Carrier and dark-fibre route survey.
  3. Heat-demand profiles by hour and month for candidate users.
  4. Parcel screening: ALR, flood, wildfire, geotechnical, road, noise and setbacks.
  5. First Nations and municipal engagement before preferred-site selection.
  6. Class 4/3 capital estimate and levelized heat cost.